About the data

W7-X's magnets took four weeks to cool

The first W7-X cooldown in 2015 brought about 450 tonnes of cold components down to temperature. Primary records explain the cooling-rate limits and adjustments to parallel helium flow paths.

Published Updated Translation reviewed
Share this article
Read the Japanese original
A W7-X half-module suspended by a crane with assembly workers.
A Wendelstein 7-X half-module during assembly.Photo: MPI for Plasma Physics/Beate Kemnitz · Image usage termsW7-X manufacture and assembly archive photo; not a photograph of the 2015 cooldown or flow adjustment.

Cooling the magnets took about four weeks. During its first cooldown in 2015, Germany's Wendelstein 7-X (W7-X) fusion experiment brought about 450 tonnes of coils, support structures and other cold components to low temperature. Running the refrigerator harder was not the only consideration. How were the many helium flow paths cooled together?

Cooling 450 tonnes at a controlled pace

W7-X is a stellarator: it confines plasma with a complex, twisted magnetic field generated by 70 superconducting coils. Cooling extends beyond the conductor to coil casings, substantial support structures and shields that limit incoming heat.

The roughly 450 tonnes cited in the report on initial refrigerator operation refers to these cold components together. It is neither the weight of the entire machine nor that of the magnets alone. Bringing them down to temperature meant commissioning a system with multiple flow paths.

A worker standing in an opening of the twisted W7-X plasma vessel.
The Wendelstein 7-X plasma vessel during manufacture.Photo: MPI for Plasma Physics/Wolfgang Filser · Image usage termsW7-X manufacture and assembly archive photo; not a photograph of the 2015 cooldown or flow adjustment.

A cooling rate of about one kelvin per hour

The report describes maintaining a cooling rate of about 1 K per hour and limiting temperature differences across the supply and return of the main circuits to 40 K. The kelvin is a unit of temperature; a difference of 1 K equals a difference of one degree Celsius. Operators monitored the pace and distribution of cooling as well as the temperature reached.

There were 70 flow paths in the casings, ten in the support structures and ten in the thermal shield, with manual valves used to adjust flow. The circuits were also cleaned before cooling began. Producing the target temperature at a refrigerator outlet and distributing the required flow through the connected circuits are separate checks.

Workers assembling a vessel and coils on a yellow rotating fixture.
Assembly of a Wendelstein 7-X half-module.Photo: MPI for Plasma Physics/Beate Kemnitz · Image usage termsW7-X manufacture and assembly archive photo; not a photograph of the 2015 cooldown or flow adjustment.

Keeping the 4 K and 5 K reports distinct

IPP's announcement of April 2, 2015 says cooling began on February 13 and the target temperature of 4 K was reached on March 10. The technical report describes reaching about 5 K in short standby mode after roughly four weeks. These descriptions have different operating and reporting contexts; they should not be presented as the same temperature measurement.

The cryostat performance assessment also distinguishes cooling the coils and their supports from cooling the surrounding thermal shield. The cold parts of the device are not all designed to run at one temperature. The photographs here document manufacture and assembly, rather than the 2015 cooldown or thermometer readings.

Five W7-X modules arranged in a ring inside the construction hall.
Wendelstein 7-X in December 2011, with all five modules on their foundations and the final outer-vessel section still to be installed.Photo: MPI for Plasma Physics/Anja Ullmann · Image usage termsW7-X manufacture and assembly archive photo; not a photograph of the 2015 cooldown or flow adjustment.

The steps between refrigeration and operation

Reaching low temperature was followed by checks of flows and heat loads and by powered magnet tests. Cooldown was one step toward plasma operation. The four-week figure is a record of initial commissioning, not the preparation time for every present-day experiment.

FI's focus is the work on pipes, valves and instrumentation between the refrigerator and the magnets, bringing them into alignment under operating conditions. Equipment delivery leaves further adjustment and testing before the system can be handed over for operation. The time spent cooling large magnets includes checking those connections.

Sources and primary documents

Information checked as of:2026-11-28
Historical account of initial commissioning in 2015. About 450 tonnes covers the cold components together. The official 4 K announcement and technical report's approximately 5 K short-standby description are distinct. About 1 K/h and 40 K are conditions reported for that cooldown, not universal present-day operating requirements.