About the data

ITER’s First Production Cryopump Reaches Target Vacuum

ITER reports that its first production cryopump reached 10⁻⁶ Pa in cold tests. Helium pumping capacity was nearly 50% higher than for the pre-production unit tested in 2025. Installation and plasma operation remain future milestones.

Published Updated Translation reviewed
Share this article
Read the Japanese original

Announcement date:2026-11-16

Torus and cryostat cryopumps in storage at ITER in 2025. This archive photograph does not show the October 2026 test.
Cryopumps in storage at ITER (2025 archive photograph)©F4E · Image usage termsF4E archive photograph published in 2025 showing several cryopumps in storage at ITER, not the first production pump during its 21–27 October 2026 test.

ITER’s first production cryopump has reached its target vacuum in a cryogenic test. In a report published on 16 November, the ITER Organization said its helium pumping capacity was nearly 50% higher than that of the pre-production unit tested in 2025. Equipment designed to evacuate the massive vacuum vessel and eventually remove exhaust gases has moved beyond factory acceptance to performance testing before installation.

Cooled to 4.5 K

From 21 to 27 October, ITER tested the production pump in a 15-cubic-metre tank at its test facility. Procured by Europe’s Fusion for Energy (F4E) and manufactured by Germany’s Research Instruments, the unit was cooled to 4.5 kelvin (about −269°C). ITER reports that tests using helium and a mixture containing hydrogen and neon achieved the target pressure of 10⁻⁶ pascal.

Testing the controls as well as the pump

ITER plans to use six cryopumps for the vacuum vessel and two for the cryostat surrounding its superconducting magnets. Along with pumping performance, the campaign examined inlet-valve modulation, isolation procedures for releasing trapped gas during regeneration, residual-gas analysis and control software. Our earlier explanation of cryopump regeneration covered the operating principle; this is a distinct result from testing a production unit.

Hydrogen test planned for 2027

ITER plans to test another production pump’s hydrogen pumping performance in 2027 and begin installing the eight pumps in 2029. The reported vacuum was achieved in a 15-cubic-metre test tank, not during operation inside ITER’s vacuum vessel or with fusion plasma.

For suppliers and system integrators, delivery is not the finish line. Vacuum performance, valves, instruments, controls and regeneration procedures must work together before commissioning.

Sources and primary documents

Information checked as of:2026-11-23
Results from a 15 m³ tank test on 21–27 October 2026. A second pump's hydrogen test in 2027 and installation starting in 2029 remain plans.

Share this article

Discuss this article