ITER tests magnet power supply chain at 55 kA

On November 23, ITER reported supplying 55 kA of direct current to a dummy load in an integrated test of its PF1 and PF6 power chain. PF2 testing is planned for December.

Published Updated Translation reviewed
Share this article
Read the Japanese original

Announcement date:2026-11-23

Workers unloading a large transformer for ITER magnet power supplies
ITER magnet transformer installation (2018, archival photograph)© ITER Organization, http://www.iter.org/ · Image usage termsInstallation of a Korean-procured magnet power transformer in 2018, not the test site of the China-supplied PF1 and PF6 chain.

ITER's giant superconducting magnets require grid electricity to be converted into very high currents. On November 23, ITER announced a successful integrated test of the China-supplied power chain for poloidal field coils PF1 and PF6, delivering 55 kA (55,000 amperes) of direct current to a dummy load. Testing took place in October.

From the grid to the magnets

Transformers step down the 400 kV AC supply from the French grid to 66 kV and then 1.05 kV. Converters use thyristors to rectify the AC into controllable direct current, carried by water-cooled aluminium busbars. The test covered the chain up to a dummy load simulating the electrical behaviour of the magnet.

Poloidal field coils create fields that control the plasma's position and shape in a tokamak. Delivering the required current requires not only magnet manufacture but system-level verification of transformers, rectifiers, busbars and protection equipment.

PF2 power supply is next

ITER China and the Institute of Plasma Physics of the Chinese Academy of Sciences (ASIPP) participated. ITER plans to test the PF2 power chain in December. The 55 kA was supplied to a dummy load rather than the magnet itself, unlike the previous TF17 coil cold test. Tests of the magnets and power supplies advance preparations for future operation.

Sources and primary documents

Information checked as of:2026-11-24
55 kA of direct current was supplied to a dummy load, not to PF coils themselves; this was not plasma operation. PF2 testing in December is planned.